If you wanted to take part in the demolition, you missed out. Matt, Gadis, Scott, Eva, Adam and Kelley have already torn down the inner walls. Matt, Kelley and Emilie have already torn out the carpet and there is not much demolition left. Eva was knocking down walls with a great deal of shoulder power, while Gadis and Matt used Matt's new tool. Richard and Robert were both there working and Richard only had one good leg.
Scott disconnected "most" of the power before we started and we found a four inch pipe with an unknown purpose in one of the walls. It was a great deal of fun and I am excited about the opportunity that will exist while youth gather there this fall and beyond.
One thing I've learned is that when Matt sets his mind on something, step back, because it will get done. He seems to collect people around him that get it done as well. I love spending time with people that make messes.
Administration, Service, Finance, Maintenance of the building that supports the people that meet there.
Tuesday, May 30, 2006
Make-A-Mess Ahead of Schedule
Tuesday, May 23, 2006
Make-A-Mess Schedule
The Administration meeting planned for this coming Saturday will be replaced by a Make-A-Mess planning session and work morning. Matt will be leading the effort.
Here is the updated schedule for Make-A-Mess. If you see something on the list that you would like to help with, please let Matt know about it.
May
- move thermostats and electric to walls that will remain
- need to talk with A/C specialist about thermostat locations
May 30 (End of Day)
- Mars Hill done with school year and Billy's office contents moved
June 3
- Demolition of flooring
- Installation of door
June 6
- Demolition of walls
June 7
- Relocation of electric
June 8
- Patching of ceiling and walls
June 12
- Prime painting walls and ceiling
June 13
- Installation of flooring
June 15
- Paint walls and ceiling
June 16
- Decorate for VBS
June 26
- VBS
Here is the updated schedule for Make-A-Mess. If you see something on the list that you would like to help with, please let Matt know about it.
May
- move thermostats and electric to walls that will remain
- need to talk with A/C specialist about thermostat locations
May 30 (End of Day)
- Mars Hill done with school year and Billy's office contents moved
June 3
- Demolition of flooring
- Installation of door
June 6
- Demolition of walls
June 7
- Relocation of electric
June 8
- Patching of ceiling and walls
June 12
- Prime painting walls and ceiling
June 13
- Installation of flooring
June 15
- Paint walls and ceiling
June 16
- Decorate for VBS
June 26
- VBS
Saturday, May 20, 2006
Work Day was a tremendous success

THANKS to all that contributed to the work day today, we really got a great deal done!
Everyone that likes to work on lists, likes to see them completed so I’ve added names to the items that were completed today.
Must Do:
- Removing construction debris from water retention basin and putting it in the dumpster ( Mike, Tim, Dan, Kim H., Matt )
- Removing junk from yard, shed and inside the building and moving it to the dumpster ( All )
- Clean out the current shared sound storage room for LCF/Tatesbrook ( Kevin, Mark, Kim F. )
- Mowing the water retention basin ( Mike, Tim, Dan, Kim H., Matt, Travis, Duane )
- Trimming the bushes around the building and parking lot ( Mike, Tim, Dan, Kim H., Matt, Travis, Duane )
- Trimming the low hanging branches in parking lot and yard ( Tim )
- Pulling the weeds in the landscaping in front of the building ( Carol, Emily, Aaron, Joshua, Tony, Michelle, Jacob, Abby, David, Caleb )
- Picking up all the brush and driving it to the dumpster ( Mike, Tim, and Adam )
Would Like to Do:
- Pulling weeds around the trees in the water retention basin ( Mike, Tim, Dan, Kim H., Matt, Travis )
- Mulching the landscaping ( Davis Family, Jones Family, Dan, Hannah )
- Dumpster diving for sunglasses wearing sandals ( Adam )
Will leave for another day:
- Edging the sidewalks ( Attempted by Kevin, Matt, Wayne )
- Repair or tear down the steeple ( will need to clear all cars and people from the area )
- Replace the air filters in the blowers ( anytime )
- Replacing outdoor lights as needed ( anytime )
- Level off the ground around the new cement and plant grass
- Change the "Water Retention Basin" to a lighted fountain like the one downtown
- Tear down some of the internal walls to fill the rest of the dumpster


Wednesday, May 10, 2006
Looking for a Job?
We have had a few opportunities show up in the last few months that I would like to offer up to the body.
- We need someone to clean the floors weekly ( buff / wax regularly as well )
- We need someone to move Herbies to the curb (Thursday night) and back (Friday Morning)
- We need someone to mow the water retention basin monthly
- We need someone to clean the church over the summer
If you are interested in any or all of this positions, please let Kevin Eby know about it!
- We need someone to clean the floors weekly ( buff / wax regularly as well )
- We need someone to move Herbies to the curb (Thursday night) and back (Friday Morning)
- We need someone to mow the water retention basin monthly
- We need someone to clean the church over the summer
If you are interested in any or all of this positions, please let Kevin Eby know about it!